Project portfolio – Royal Arsenal, Phase 9 Project Summary Project Value to NSP (500k) 2No. Mechanical push/pull AOV shafts with adiabatic cooling - all blocks above 20 levels 6000m 2 Car Park to be partitioned in phase 1 and then released in full 12months later in Phase 2. featuring temporary extract location, moving and using the same main extract fans from Phase 1 (most economically viable). Equipment: 13No. 60N Induction Fans 2No. 23.05m3s - 1 Extract fans (1600mm dia ) 15No. CO Detectors 60No. Smoke Detectors Attenuation to meet NR55 (internally) & 55dBA @ 3m (externally)